Does your arc flash study need to be redone?
By Jay Prigmore, Ph.D., P.E.8 min read
Reviewed against the editions listed under Sources reviewed on .
The question often arrives in the same form: someone opens an arc flash study, finds “IEEE 1584-2002” in the methodology section, and wants to know whether the whole thing has to be thrown out. A superseded edition does not by itself make a study wrong. What IEEE Std. 1584-2018 did change is which inputs the model asks for, and many 2002-era studies do not record them. In my experience, the decision often turns on that silence more than on the edition number itself.
What changed, briefly
The full technical account of the model changes (the test program behind the 2018 edition and how the model changed shape as a result) is written up at length on a separate site: IEEE 1584-2018 vs 2002: what actually changed(opens in a new tab, external site). This page is about the decision rather than the model, so what follows is only the part that bears on it.
Three consequences of IEEE Std. 1584-2018 matter to anyone holding a study built on IEEE Std. 1584-2002:
- Electrode configuration became an explicit input. How the conductors are arranged (their orientation, and whether the arc terminates in open air, inside a box, or against an insulating barrier) changes how energy is directed toward a worker. The 2018 model asks which arrangement applies. The 2002 model separated open air from enclosed equipment but did not ask about orientation, so many studies built on it never recorded the answer, and it may not be recoverable from the document.
- Enclosure geometry entered the calculation. The physical size of the box is treated as affecting the result rather than as incidental. A study that never recorded enclosure dimensions may need a trip back to the field before it can be run under the newer model.
- The applicability envelope moved. Each edition states the range of voltages, conductor gaps, and fault currents its model is valid within, and those ranges are not the same. Equipment that sat comfortably inside the 2002 model's range may sit near or outside the 2018 model's, or the reverse. Read the ranges in your own copy of each guide and compare them against what your study actually modeled.
The 2018 edition also handles the variation in arcing current differently. Both editions recognize that the arcing current is not a single deterministic value and that a lower-than-expected arcing current can hold an upstream protective device in a slower part of its curve, producing a longer clearing time and therefore more incident energy. In my experience this step is often skipped in studies of every vintage, so it is a good one to look for early.
Why a 2002 study is not automatically wrong
Two things are often conflated: whether a study used a superseded model, and whether its results are unsafe. They are not the same question. A 2002-model study of a facility whose equipment sits squarely inside that model's range, whose protective devices have not been re-set, whose transformer has not been replaced, and whose assumptions are all written down is a document that can be examined and checked. A 2018-model study that never states its electrode configuration is not made more reliable by its edition alone.
In practice, the newer edition changed what a study has to record to run its model. It made explicit several things that used to be assumptions, and an assumption that has been made explicit is one a reviewer can check. That is why the edition question often turns into a documentation question.
Four things the decision often turns on
When this question comes up in practice, it usually comes down to four points. None of them requires recalculating anything. The first three can be answered from the study document you already have. The fourth also needs the current state of the plant.
- Does the study state its edition and model at all? If not, the rest of this list is hard to evaluate, and that is the finding.
- Is the equipment inside the stated applicability limits? A result produced outside the range the model is valid within should not be relied on without further justification, and some studies do not flag when they have gone outside it.
- Was the reduced-arcing-current case run? If the study reports one incident energy value per bus with no second case and no narrative explaining its absence, the governing value may not be the one on the label.
- Does the study still describe the system you have? The edition matters little if a transformer was swapped, a tie was added, or a trip unit was re-set since the study was issued. A model that no longer matches the plant needs attention under either edition.
Where the periodic review fits
In NFPA 70E-2018, 130.5(G) addresses two triggers for revisiting an incident energy analysis: a system change that could affect its results, and the passage of 5 years. As of November 2026 the current edition is NFPA 70E-2027, so read the edition that applies to you for the current interval and wording.
The practical point is that a system change, not the calendar, is often what makes a study stale. Facilities change continuously and quietly. The periodic review is simply the moment somebody finally has to look, which is why the edition question and the five-year question tend to arrive in the same email. If you are preparing for one, the edition is one of several things to check, and often not the most urgent.
What to do with an old study
Start by reading it. A full restudy can be a large expense, and it is sometimes the right answer. A cheaper first step is to establish what the existing document supports: which model, which inputs, which assumptions are stated, which are silent, and whether the plant still matches. With that evidence in hand, the redo-or-not conversation with your Engineer of Record, who makes the call, is easier to have.
Check the study you already have.
Edition, model limits, electrode configuration and the sensitivity case, each tied to a page.
$149 covers the first 50 pages, then $1.25 per page. Typically delivered within 1 hour. May take longer when demand is high.
An automated report, using checklists authored by a Ph.D., P.E. It is not an engineering determination.
See a sample report. Our samples are anonymized samples from pre-launch test documents.
FAQ
IEEE 1584 editions: common questions
Is an arc flash study done to IEEE 1584-2002 invalid?
Not because of the edition alone. A newer edition does not by itself make earlier work wrong, and the 2002 edition was the current one until 2018. A study on the older model is more likely to be silent about inputs the newer model asks for, which can make a value harder to explain if anyone later asks how it was reached. Whether that silence matters at your facility is a determination for your Engineer of Record and your AHJ.
How do I tell which edition my study used?
A study that documents its methodology says so, usually in the methodology or assumptions section near the front, and often again in the software settings appendix at the back. If you cannot find an edition stated anywhere in the document, that is itself the finding: a study that does not record which model produced its numbers is hard for anyone to check, including the engineer who inherits it from you.
Does new software mean my study is on the new edition?
Not by itself. Software may offer both models, and which one a given project used depends on the settings in that project file at the time the study was run. Re-opening an old project in a new version of the software does not by itself re-run it. The study document is the place to look for what was actually done.
How often does an arc flash risk assessment have to be reviewed?
In NFPA 70E-2018, 130.5(G) addresses two triggers for revisiting an incident energy analysis: a system change that could affect its results, and the passage of 5 years. The first is easier to miss, because it depends on an event and nothing sends a reminder. As of November 2026 the current edition is NFPA 70E-2027, so read the edition that applies to you for the current interval and wording.
Can you tell me whether I need a new study?
No. That call is not one an automated product can make. What the arc flash study review on this site does is read the study you already have and report what it does and does not establish: which edition and model it states, whether the equipment falls inside the applicability limits of that model, whether electrode configuration and gap are documented, and whether the reduced-arcing-current case appears anywhere. That is the evidence the decision needs. The decision itself is the Engineer of Record’s.
Standards and sources
Sources reviewed for this article
- IEEE Std. 1584-2018, IEEE Guide for Performing Arc-Flash Hazard Calculations.
- IEEE Std. 1584-2002, IEEE Guide for Performing Arc-Flash Hazard Calculations.
- NFPA 70E-2018, Standard for Electrical Safety in the Workplace.
Named in NFPA's November 2026 document listing and listed so you can find them.
- NFPA 70E-2027, Standard for Electrical Safety in the Workplace.
Need a professional engineer? Contact PEFG at info@pefgconsulting.com.